Skip to content
Back to Blog
Quoting·6 min read

By Sofoclis Patsalosavvis — Construction Director, MyQS

How to Calculate Preliminaries on a Construction Project

How to Calculate Preliminaries on a Construction Project

Quick Answer: Preliminaries are the indirect costs of running a construction project — site setup, management, welfare, and equipment. To calculate them, list every project-wide cost that isn't tied to a specific trade, total them up, and add the figure as a separate section in your quote or tender.

If you've ever underpriced a job and wondered where your profit went, prelims are often the culprit. Most tradespeople are good at pricing the work itself — labour, materials, plant. But the costs of running the project? Those get forgotten, and that's where the money leaks out.

This guide explains exactly how to calculate preliminaries on a construction project, what to include, and how to make sure you're covering yourself every time you price a job.

What Are Preliminaries in Construction?

Preliminaries — or prelims — are costs that apply to the whole project rather than to any single trade or work package. They're not bricks, not labour on the walls, not the roof tiles. They're everything needed to make the project happen.

Think of it this way: if you strip out all the trade work, what's left? That's your prelims.

Common examples include:

  • Site management and supervision
  • Welfare facilities (toilets, canteen, drying room)
  • Site hoarding and security fencing
  • Scaffolding (if project-wide rather than trade-specific)
  • Temporary power, water, and lighting
  • Skips and waste removal
  • Site insurance and all-risk cover
  • Health and safety signage and documentation
  • Transport and fuel costs
  • Tools and small plant hired for the duration
  • Project management time

Why Getting Prelims Wrong Costs You Money

A lot of builders and contractors lump everything together or just add a percentage and hope for the best. That's a risky approach.

On a small domestic extension, prelims might be 8–15% of the total build cost. On a larger commercial project, that figure can climb to 20% or more. If you miss them entirely, you're eating into your margin from day one.

The bigger the job and the longer the programme, the more your prelims will cost. A two-week kitchen refit has very different prelim requirements to a six-month new build.

How to Calculate Preliminaries Step by Step

There's no single formula — prelims are project-specific. But there is a clear process you can follow every time.

  1. Review the project scope and programme. Before you price anything, understand how long the job will take and what the site conditions are. Duration drives a lot of your prelim costs.
  2. List every site-wide cost you can think of. Go through each category: management, welfare, access, plant, waste, utilities, insurance, health and safety. Don't skip anything because it seems small.
  3. Split costs into fixed and time-related. Fixed costs happen once — setting up hoarding, for example. Time-related costs recur over the programme — site manager's wages, skip hire, toilet rental. Keep these separate so you can adjust if the programme changes.
  4. Quantify each item. Get actual costs where you can. Call your skip hire company. Check your insurance premium. Price the welfare unit rental. Estimated figures come back to bite you.
  5. Multiply time-related costs by duration. If your site manager costs £800 a week and the project runs for 12 weeks, that's £9,600. Do this for every recurring item.
  6. Add a contingency allowance. Projects run over. Weather delays happen. Add 5–10% to your prelim total to protect yourself.
  7. Present prelims as a separate section in your quote. Don't bury them in your trade costs. A clear prelims section shows clients you've thought the job through — and it's easier to justify if they query anything.

Worked Example: Residential Extension

Here's a straightforward example to show how the numbers stack up on a typical 16-week single-storey rear extension.

  • Site manager (part-time, 2 days/week at £350/day x 16 weeks): £11,200
  • Portable toilet hire (16 weeks at £35/week): £560
  • Skip hire (6 skips at £280 each): £1,680
  • Temporary power supply and usage: £400
  • Site hoarding setup (fixed cost): £600
  • Health and safety file and documentation: £300
  • Site insurance top-up: £450
  • Fuel and transport across programme: £800
  • Contingency (8%): £1,279

Total preliminaries: approximately £17,269

That's money you'd lose if you didn't price it in. On a £120,000 build, that's over 14% — well worth calculating properly.

Common Mistakes to Avoid

  • Using a blanket percentage without checking. A rule of thumb only works if it's grounded in real costs. Always verify.
  • Forgetting management time. Your time running the project has a cost, even if you're the business owner.
  • Not accounting for programme overruns. Build in contingency. It's not pessimism — it's professionalism.
  • Combining prelims with trade costs. Keep them separate so you know where your money is going.

How Software Can Speed This Up

Pricing prelims manually every time takes effort, especially when you're juggling multiple quotes. Tools like MyQS are built for exactly this — helping UK tradespeople and contractors build accurate, itemised quotes quickly, with prelims included as a proper, structured section rather than an afterthought. When your template is set up right, you can price a job in a fraction of the time and be confident nothing's been missed.

FAQ: Preliminaries on Construction Projects

Q: What percentage should preliminaries be of the total build cost?
A: On most residential projects in the UK, prelims typically fall between 8% and 15% of the total build cost. On larger or more complex projects, this can rise to 20% or higher. Always calculate from actual costs rather than relying purely on a percentage.

Q: Are preliminaries the same as overhead and profit?
A: No. Prelims cover site-specific project costs. Overheads are your business running costs — office, phone, accountant, van when not on site. Profit is your margin on top of everything. All three are separate and should be priced separately.

Q: Do I need to show prelims separately in a quote?
A: There's no legal requirement, but it's good practice. A transparent quote builds trust with clients and makes it easier to explain your pricing. It also protects you — if the project scope changes, you have a clear basis for adjusting your prelim costs.

Conclusion

Prelims aren't optional extras — they're real costs that have to come from somewhere. If you don't price them properly, they come out of your profit.

The process isn't complicated: list everything, split fixed from time-related, multiply by duration, add contingency, and present it clearly. Do that consistently and you'll stop losing money on the jobs you thought you'd priced correctly.

Want to make prelim pricing faster and more accurate on every quote you send? Head to myqs.ai and see how MyQS helps UK tradespeople build professional, detailed quotes — prelims included.

About MyQS

MyQS generates professional construction quotes from photos, floor plans or voice. Built by a QS for UK trades.

Start Free — No card needed